Major construction this summer on I-465 will affect commutes

Construction on I-69 close to the I-465 interchange.  - Liz DeSantis, WFIU/WTIU News

Construction on I-69 close to the I-465 interchange.

Liz DeSantis, WFIU/WTIU News

Heavy construction is underway on I-465, much of which will take place this summer

All I-465 eastbound lanes between I-65 and I-70 will be closed to traffic from June 2 to the 21. All westbound lanes will be closed July 7 to the 29. 

i-69 eastbound

i-69 westbound

Read more: A year from completion, I-69 remains divisive

Indiana Department of Transportation Communications Director Natalie Garrett said the project will add lane capacity to I-465. 

“We'll have hundreds of crews out 24 hours a day, seven days a week completing this work so we can get done what we needed to get done and get out,” she said. 

Garrett told WFIU that an official detour route will follow I-65 and I-70 through the south split. She recommended commuters consider their routes beforehand. 

Read more: Indiana Senate passes bill authorizing speed cameras in highway work sites

“There could be some increased congestion and some delays, so plan ahead,” Garrett said.

Construction on the interchange will last through 2024 although according to INDOT some travel restrictions may last into the next year. 

Work will also continue on I-69 and I-465 on the northeast side of Indianapolis for the Clear Path project. It includes new lanes and 14 new bridges to improve traffic flow. Construction began early last year and will end by 2026. 

 

Support independent journalism today. You rely on WFYI to stay informed, and we depend on you to make our work possible. Donate to power our nonprofit reporting today. Give now.

 

Related News

Number of IMPD shootings still high in Indianapolis
Six shot Christmas Day on Indy’s northeast side
Over 100 unhoused residents died in Indy, sparks calls for progress at their memorial