November 11, 2015

Columbus Municipal Airport's Runway Overhaul Completed

COLUMBUS, Ind. (AP) — Work has been completed on an overhaul of a runway at a southern Indiana airport that officials expect will boost traffic.

The $5 million project at the Columbus Municipal Airport included removing 9 inches of a runway's asphalt surface and replacing it with 10 inches of concrete.

Airport Director Brian Payne tells The Republic that poor drainage along the runway led to water accumulating in the asphalt. That caused the surface to deteriorate and become a safety hazard. The drainage has been improved and the new runway is fully grooved so that planes are better able to take off and land during bad weather.

The project took three months to complete. The concrete runway is expected to last at least 30 years.

Support independent journalism today. You rely on WFYI to stay informed, and we depend on you to make our work possible. Donate to power our nonprofit reporting today. Give now.

 

Related News

Indianapolis budget for 2025 proposes $1.6 billion in spending
Kamala Harris hits campaign trail with speech in Indianapolis at national sorority gathering
The Secret Service is investigating how a gunman who shot and injured Trump was able to get so close